Contract No: HY/2019/18 Wanchai Development
Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 4) Environmental Permit no. EP-364/2009/H, Further Evironmental permit nos.
fep-01/364/2009, FEp-06/364/2009/a, FEP-07/364/2009/H, FEP-10/364/2009/B and
FEP-11/364/2009/E Monthly Environmental Monitoring &
Audit Report
- OctoBER 2020 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
November 2020 |
2.2 Scope of
the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3 status of
regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise
Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7 Cumulative Construction Impact due to the
Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual
Contracts under the Project
Table 2.3 Contact Details of
Key Personnel
Table 3.1 Summary of the current
status on licences and/or permits on environmental
protection pertinent to the Project
Table 3.4 Cumulative Summary of
Valid Licences and Permits under Contract no.
Table 3.5 Summary of submission
status under FEP-01/364/2009
Table 3.8 Cumulative Summary of
Valid Licences and Permits under Contract no.
Table 3.9 Summary of submission
status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid License and
Permits under Contract no. HY/2009/19
Table 3.11 Summary
of submission status under FEP-07/364/2009/G
Table 3.14 Cumulative Summary of Valid License and
Permits under Contract no. HY/2010/08
Table 3.15 Summary
of submission status under FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid License and
Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring
Stations
Table 4.3 Air Quality Monitoring
Stations
Table
5.2 Noise Monitoring Station for Contract no.HK/2009/02
Table 5.3 Noise Monitoring
Stations for Contract no. HY/2009/15
Table 5.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real Time Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.13 Air Quality Monitoring
Station for Contract no. HY/2009/19
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring
Stations for Contract no. HY/2011/08
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Table 5.20
Details of Waste Disposal for Contract no. HY/2009/15
Table 5.21
Details of Waste Disposal for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal for Contract no.
HK/2012/08
Table 5.23 Details of Waste Disposal for Contract no.
HY/2010/08
Table 5.24 Details of Waste Disposal for Contract no. HY/2011/08
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics
on Complaints
Table 9.2 Cumulative Statistics
on Successful Prosecutions
Table 10.1 Summary of Key
Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting period
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix 4.2 Copies
of Calibration Certificates
Appendix 5.1 Monitoring
Schedule for Reporting period and Coming month
Appendix 5.2 Noise
Monitoring Results and Graphical Presentations
Appendix 5.3 Air
Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1 Event
Action Plans
Appendix 9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Tunnel water seepage rectification works
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
·
Bridge noise enclosure construction & road works.
·
Hing Fat Street road works.
·
Soft Landscaping works.
·
Open area hard paving.
·
D12 & Open Area fire main laying works.
·
D9 to D12 and P22 to P25 drainage works.
·
Rumsey Street modification works.
·
EVB injection grouting work.
·
F5-F15 fender work.
·
Watson Road Roadworks.
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009/B
·
Drainage improvement works
·
Utility diversion works
·
Junction modification
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Nil
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Future Key Issues
i.
In the coming reporting period, the principal work activities of
individual contracts are anticipated as follows:
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel water seepage rectification works
·
Demolition of Site Office.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
·
Bridge noise enclosure construction & road works.
·
Hing Fat Street road works.
·
Soft landscaping works.
·
Open area hard paving.
·
D12 & Open Area fire main laying works.
·
D9 to D12 and P22 to P25 drainage works.
·
Rumsey Street modification works.
·
EVB injection grouting work
·
IEC Eastbound Corbel construction
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Drainage improvement works
·
Utility diversion works
·
Junction modification
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
1.1.1. Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-364/2009/H and Further Environmental permit nos. FEP-01/364/2009, FEP-06/364/2009/A, FEP-07/364/2009/H, FEP-10/364/2009/B
and FEP-11/364/2009/E to implement the Environmental Monitoring
and Audit (EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2. This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3. This report
documents the finding of EM&A works for Environmental
Permit (EP) no. EP-364/2009/H, Further Environmental Permit (FEP) nos. FEP-01/364/2009, FEP-06/364/2009/A, FEP-07/364/2009/H, FEP-10/364/2009/B
and FEP-11/364/2009/E during the period 27 September 2020
to 26 October 2020.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project Background –
summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring Requirements –
summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results –
summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit –
summarizes the auditing
of monitoring results, all
exceedances
environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1. “Wan Chai Development phase II and
Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern
Corridor Link” (hereafter called “the Project”) are Designated Project (DP) under the Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO).
The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan
Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008
respectively.
2.1.2. The key purpose of Wan Chai Development
Phase II (WDII) is to provide land at Wan Chai North and North Point for
construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link
(CWB). Land formed under the project will be developed as a world-class
waterfront promenade joining that at the new Central waterfront for public
enjoyment.
2.1.3. There is a compelling and present need for
the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1. Design and
Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and
its road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL)
includes:
·
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
·
Associated road lighting, road signing, traffic control and surveillance
system; and
·
Other associated works.
2.2.3. The project also contains various Schedule
2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows
the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2
Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1. Due to the multi-contract nature of the
Project, there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2. The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details of
Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield
Depot – Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central
Interchange |
DP1 |
21 April 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works |
DP1,
DP2 |
25
August 2011 (Completed) |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 (Completed) |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1. Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2. The proposed project organization and
lines of communication with respect to environmental protection works are shown
in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Senior Resident Engineer |
Mr. S.K. Lo |
3519 9033 |
2587
1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. David Kwan |
3650 1888 |
3665
0106 |
|
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
2827
9996 |
Environmental Officer |
Mr. Samuel Chan |
9646-5780 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. William Leung |
3758 8879 |
3757
8901 |
Site Agent |
Mr. William Luk |
3758 6868 |
|||
Deputy Site Agent |
Mr. Andrew Cheng |
9161 9446 |
|||
Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Assistant Environmental Officer |
Mr. Nelson Wong |
6387 3939 |
|||
Construction Manager (Marine) |
Mr. Wingo Wong |
9300 2625 |
|||
Construction Manager (Noise Barrier) |
Mr. Jerry Siu |
9493 3664 |
|||
Construction Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Agent |
Mr. Patrick Ho |
3557 6405 |
2566 2192 |
||
Environmental Officer |
Mr. Gabriel
Wong |
6114
9590 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Mr.
Chris Leung |
9210
7116 |
2566
8061 |
Project
Manager |
Mr.
Chan Ying Lun |
3418
3001 |
|||
Site
Agent |
Mr. Danny
Lee |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Norman Croker |
2823 1410 |
21406799 |
Environmental
Officer |
Mr. Y.K. Wu |
3973
1977 |
|||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting period, the principal work activities of individual
contracts are included as follows:
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel water seepage rectification works
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/H
·
Bridge noise enclosure construction & road works.
·
Hing Fat Street road works.
·
Soft Landscaping works.
·
Open area hard paving.
·
D12 & Open Area fire main laying works.
·
D9 to D12 and P22 to P25 drainage works.
·
Rumsey Street modification works.
·
EVB injection grouting work.
·
F5-F15 fender work.
·
Watson Road Roadworks.
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Drainage improvement works
·
Utility diversion works
·
Junction modification
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Nil
2.4.4.
In coming reporting period, the principal work activities of individual
contracts are anticipated as follows:
·
Tunnel water seepage rectification works
·
Demolition of Site Office.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/H
·
Bridge noise enclosure construction & road works.
·
Hing Fat Street road works.
·
Soft landscaping works.
·
Open area hard paving.
·
D12 & Open Area fire main laying works.
·
D9 to D12 and P22 to P25 drainage works.
·
Rumsey Street modification works.
·
EVB injection grouting work
·
IEC Eastbound Corbel construction
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Drainage improvement works
·
Utility diversion works
·
Junction modification
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Nil
3.1.1.
A summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status on licences
and/or permits on environmental protection pertinent to the Project
Permits
and/or Licenses |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Surrendered |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Surrendered |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
Surrendered |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further
Environmental Permit |
FEP-08/356/2009 |
1 Aug 2016 |
Surrendered |
Environmental Permit |
EP-364/2009/H |
22 Apr 2020 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Surrendered |
|
Further Environmental Permit |
12 Jul 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Surrendered |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Apr 2020 |
Valid |
|
Further Environmental Permit |
15 Jun 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 Mar 2013 |
Surrendered |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug 2016 |
Surrendered |
Environmental Permit |
EP-376/2009 |
13 Nov 2009 |
Valid |
Further Environmental Permit |
FEP-01/376/2009 |
31 Mar 2015 |
Surrendered |
Further Environmental Permit |
FEP-02/376/2009 |
1 Aug 2016 |
Surrendered |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
3.1.3.
The construction works was completed and the FEP-03/364/2009 was
surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai Development
Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.6. As confirmed with WDII RSS and with
respect to the joint inspection conducted with IEC on 25 May 2018, RSS, ET and
IEC share the view that there is no adverse environmental impact of remaining
works under Contract HK/2009/01 and the respective environmental site
inspection and associated monitoring station were temporary suspended from 26
May 2018 onwards. FEP-02/364/2009 was surrendered by the Contractor on 3
September 2018.
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
3.1.7.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract
no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
27 Mar
2020 |
Surrendered |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
N/A |
N/A |
N/A |
N/A |
Water
Discharge License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Expired |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.5 Summary of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date
of
Submission |
Condition 2.7
and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov
2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan
2012 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.8.
The Construction works under HY/2009/15 was confirm completed by the RSS
from 27 October 2017 onwards. The weekly site audit inspection and environmental
monitoring station were temporary suspended and no longer associated with
HY/2009/15 from 27 October 2017 onwards.
3.1.9.
As confirmed by CWB RSS, the seabed reinstatement works was resumed
under Contract HY/2009/15 at EX-PCWA area on 26 June 2019 and the weekly site
audit inspection and the associated monitoring station for HY/2009/15 were
resumed from 26 June 2019 onwards and report under FEP-04/356/2009 in
EP-356/2009 Monthly EM&A Report.
3.1.10.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Construction Noise Permit |
N/A |
N/A |
N/A |
N/A |
Water Discharge License (Discharge
at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Surrendered |
Table 3.9 Summary of submission status under
FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 Mar
2011 |
Amendment for Management
Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar
2011 |
Condition 2.8 |
Location Plan |
15 Mar
2011 |
Condition 2.9 |
Noise Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape
Plan (Rev.5) |
9 Oct 2020 |
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
3.1.11.
The
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-07/364/2009/H for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
22 Apr 2020 |
N/A |
Valid |
|
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Notification
of Works (further proposed change to the particulars) Under APCO |
415587 |
11 Apr 2017 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10
Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24
Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7013285 |
21
Jul 2011 |
N/A |
Valid |
Construction Noise Permits (CNP) for
non-piling equipment |
GW-RS0328-20 |
22-May-20 |
24-May-20 to 21-Nov-20 |
Valid |
GW-RS0584-20 |
28-Aug-20 |
31-Aug-20 to 20-Oct-20 |
Expired |
|
GW-RS0592-20 |
28-Aug-20 |
31-Aug-20 to 20-Dec-20 |
Valid |
|
GW-RS0435-20 |
29-Jun-20 |
02-Jul-20 to 24-Dec-20 |
Valid |
|
GW-RS0628-20 |
09-Sep-20 |
11-Sep-20 to 03-Nov-20 |
Valid |
|
GW-RS0579-20 |
27-Aug-20 |
31-Aug-20 to 26-Feb-21 |
Valid |
|
Water
Discharge License |
WT00025282-2016 |
15 Sep
2016 |
30 Sep 2021 |
Valid |
WT00035697-2020 |
19 Jun
2020 |
30-Jun-25 |
Valid |
Table 3.11 Summary of submission status under
FEP-07/364/2009/H
EP Condition |
Submission |
Date
of
Submission |
Condition 2.13 |
Landscape Plan (Rev.7) |
23 March 2020 |
Condition 2.9 |
Noise Management Plan (Rev.5) |
29 May
2019 |
Contract
no. HY/2010/08 –Central – Wanchai Bypass Tunnel – Tunnel (Slip Road 8) under
FEP-10/364/2009/B
3.1.12.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-10/364/2009/B for contract no.
HY/2010/08 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-10/364/2009/B |
26
Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26
Jul 2013 |
NA |
Valid |
|
Notification
of Works Under APCO |
357176 |
2
Apr 2013 |
NA |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
27
Mar 2013 |
NA |
Valid |
Billing
Account under Waste Disposal Ordinance |
7017170 |
27
Mar 2013 |
NA |
Valid |
Water Discharge License |
WT00031281-2018 |
31
Jul 2018 |
31
Jul 2023 |
Surrendered |
Construction Noise Permits (CNP) for
non-piling equipment |
GW-RS0741-20 |
4 May 2020 |
4 May 2020 to 29 Oct 2020 |
Valid |
GW-RS0416-20 |
4 May 2020 |
4 May 2020 to 29 Oct 2020 |
Valid |
|
GW-RS0360-20 |
26 Jun 2020 |
29 Jun 2020 to 22 Dec 2020 |
Valid |
|
GW-RS0678-20 |
8 Jun 2020 |
8 Jun 2020 to 30 Oct 2020 |
Valid |
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.2) |
19 May 2014 |
Condition 2.16 |
Additional
Mitigation Plan (Rev.6) |
24 September 2020 |
C
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
3.1.13.
The current status on licenses and/or permits on environmental
protection pertinent and submission under FEP-11/364/2009/E for contract no.
HY/2011/08 showed in Table 3.16 and Table 3.17.
Table 3.16 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2011/08
Permits
and/or Licenses |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
N/A |
Valid |
Notification
of Works Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
5213-121-L2837-01 |
19 Apr 2016 |
N/A |
Valid |
5213-151-L2837-02 |
24 May 2016 |
N/A |
Valid |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Valid |
|
5213-134-L2952-01 |
12 May 2017 |
N/A |
Valid |
|
Billing
Account under Waste Disposal Ordinance |
7019640 |
27 Mar 2014 |
N/A |
|
Construction Noise Permits (CNP) for
non-piling equipment |
GW-RS0190-20 |
25 Mar 2020 |
30 Mar 2019
to 29 Sep 2020 |
Expired |
GW-RS0191-20 |
25 Mar 2020 |
30 Mar 2020
to 29 Sep 2020 |
Expired |
|
GW-RS0192-20 |
25 Mar 2020 |
30 Mar 2020
to 29 Sep 2020 |
Expired |
|
GW-RS0214-20 |
1 Apr 2020 |
10 Apr 2020
to 9 Oct 2020 |
Expired |
|
30 Jul 2020 |
3 Aug 2020
to 29 Jan 2021 |
Valid |
||
14 Aug 2020 |
19 Aug 2020
to 22 Jan 2021 |
Valid |
||
GW-RS0558-20 |
19 Aug 2020 |
22 Aug 2020
to 3 Feb 2021 |
Valid |
|
Water
Discharge License |
WT00025858-2016 |
17
Oct 2016 |
31
Oct 2021 |
Valid |
WT00026829-2017 |
14
Jun 2017 |
31
Jan 2022 |
Valid |
|
WT00027343-2017 |
01
Mar 2017 |
31
Mar 2022 |
Valid |
|
WT00028343-2017 |
09
Aug 2017 |
31
Aug 2022 |
Valid |
Table 3.17 Summary of submission status under
FEP-11/364/2009/E
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.4) |
08 Nov 2016 |
Condition 2.14 |
Landscape Plan (Rev.5) |
13 Feb 2020 |
Condition 2.13 a) |
Operational Air Quality Management
Plan for West Ventilation Building (Rev.0) |
25 Nov 2014 |
Condition 2.13 b) |
Operational Air Quality Management
Plan for Central Ventilation Building (Rev.0) |
03 Mar 2017 |
Condition 2.13 c) |
Operational Air Quality Management
Plan for East Ventilation Building and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Condition 2.13 d) |
Operational Air Quality Management
Plan for an Electrostatic Precipitator system for EVB Operation (Rev.0) |
06 Apr 2017 |
Condition 2.13 e) |
Operational Air Quality Management
Plan for ventilation system of Eastern Portal of the CWB Tunnel (Rev.0) |
23 Oct 2016 |
Noise
Monitoring Stations
4.1.1.
The noise
monitoring stations for the Project are listed and shown in Table 4.1
and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.1 Noise Monitoring
Stations
Station |
Description |
M1a*** |
Footbridge for Ex-Harbour Road Sports Centre |
M2b |
Noon-day
Gun Area |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
M7a |
Harbour
Building |
M7e* |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8** |
City Hall |
Remark *: Location ID has been updated from M7 to
M8 for City Hall
Remark **: M7e has become a reference station
starting from 7 Aug 2012
Remarks***: The location ID of monitoring station
M1a was updated as “Footbridge for Ex-Harbour Road Sports Centre” in May 2017.
Real time Noise Monitoring Stations
4.1.2.
The noise
monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Hong Kong Electric
Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee
Mo Fan Memorial School |
Tin Hau |
RTN4 |
Causeway Bay
Community Centre |
Noise
Monitoring Parameters, Frequency and Duration
4.1.3.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the designated monitoring
stations. The monitoring frequency shall depend on the scale of the
construction activities. The following is an initial guide on the regular
monitoring frequency for each station on a weekly basis when noise generating
activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the designated monitoring
stations. The following is an initial guide on the regular monitoring frequency
for each station on a 24 - hours basis when noise generating activities are
underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
· One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
· One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction works are extended to include works during the hours of
1900 – 0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring
Equipment
4.1.7.
As referred to in the Technical Memorandum ™ issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
4.1.9.
The sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency before deployment
to the site and during each site visit. Measurements will be accepted as valid
only if the calibration level from before and after the noise measurement agree
to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air quality monitoring stations for the Project are listed and shown
in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour
Grand Hotel Boundary Wall** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway
Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
MA1b |
Harbour Building |
Central |
Remarks*: As per the
ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB site office at Wanchai Waterfront
Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as “Oil Street Site Office” in April 2013. The location ID of monitoring
station CMA1b was updated as “Harbour Grand Hotel Boundary Wall” with respect to the fine adjustment of monitoring
station from the Oil Street Site Office to Harbour Grand Hotel Boundary Wall
from 05 June 2017 onwards due to demolition of Oil Street Site Office.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air QUALITY Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured to indicate the
impacts of construction dust on air quality. The 24-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix
B.
4.2.3.
All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., shall be recorded down
in detail.
4.2.4.
For regular impact monitoring, the sampling frequency of at least once
in every six days, shall be strictly observed at all the monitoring stations
for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency
of at least three times in every six days should be undertaken when the highest
dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the following
specifications shall be used for carrying out the 1-hour and 24-hour TSP
monitoring:
· 0.6 – 1.7 m3 per minute
adjustable flow range;
· Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
· Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
· Capable of providing a minimum exposed
area of 406 cm2;
· Flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
· Equipped with a shelter to protect the
filter and sampler;
· Incorporated with an electronic mass
flow rate controller or other equivalent devices;
· Equipped with a flow recorder for
continuous monitoring;
· Provided with a peaked roof inlet;
· Incorporated with a manometer;
· Able to hold and seal the filter paper
to the sampler housing at horizontal position;
· Easily changeable filter; and
· Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment shall be conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard
shall be traceable to the internationally recognized primary standard and be
calibrated annually. The concern parties such as IEC shall properly document
the calibration data for future reference. All the data should be converted
into standard temperature and pressure condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and humidity control, and
equipped with necessary measuring and conditioning instruments to handle the
dust samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of size 8” x 10” shall be labelled before sampling. It
shall be a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24 hours and be pre-weighed before use for
the sampling.
4.2.9.
After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly calibrated against a traceable standard.
4.2.10.
All the collected samples shall be kept in a good condition for 6 months
before disposal.
4.2.11.
Current calibration certificates of equipments are presented in Appendix 4.2.
5.0.1.
The environmental monitoring will be implemented based on the division
of works areas of each designated project managed under different contracts
with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure 2.1 and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting period, the concurrent contracts are as follows:
Contract no.
HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
Contract no.
HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB)– Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.0.3.
The environment monitoring schedules for reporting period and coming
month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline noise level was performed from
11 April 2011 to 8 June 2011. Then the
report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and
was approved by ER by January 2012. The
new baseline is used for the noise calculation starting from January 2012.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.1.2
The commencement of construction works for HK/2009/02 under
FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring
stations are summarized in Table 5.2 below.
Table 5.2 Noise Monitoring Station
for Contract no HK/2009/02
Station |
Description |
M1a |
Footbridge for Ex-Harbour Road Sports Centre |
5.1.3
No action or limit level exceedance was recorded in the reporting
period.
5.1.4
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/H
5.1.5 Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division
of noise monitoring stations are summarized in Table 5.4 below.
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
M7a |
Harbour Building |
5.1.6
Limit level exceedance was recorded at M4b - Victoria Centre on 28 September
2020 in the reporting period.
5.1.7
Concreting work to the road adjacent to Toyota maintenance shop at
Watson Road was carried out under HY/2009/19 around the monitoring location.
Temporary noise barrier was erected as noise mitigation measure for the works.
Meanwhile, non-CWB project material handling work immediately next to the
monitoring station was observed as the major noise contribution during
monitoring. As such, the exceedance was considered as non-Project related.
5.1.8
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel
(Slip Raod 8 Section) under FEP-10/364/2009/B
5.1.9 The commencement
of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02
September 2013. The proposed divisions of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5 Noise Monitoring Stations for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10
As confirmed with CWB RSS, junction modification works in Central area would
be conducted by Contract HY/2010/08 starting from July 2018 and tentatively
completed in September 2018. The noise monitoring station M7e - International
Finance Centre (Eastern End of Podium), M7w - International Finance Centre
(Western End of Podium) and M8 – City Hall would tentatively associated with Contract
HY/2010/08.
5.1.11
As confirmed with Resident Site Staff, the junction modification under
Contract HY/2010/08 at Central Area was generally completed while the remaining
works was considered to be no adverse impact and not related to DP works. As
such, The noise monitoring station M7e - International Finance Centre (Eastern
End of Podium), M7w - International Finance Centre (Western End of Podium) and
M8 – City Hall would no longer associated with Contract HY/2010/08 in August
2019 reporting month.
5.1.12
No action or limit level exceedance was recorded in the reporting
period.
5.1.13
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.1.14 Noise
monitoring for the Central Interchange works under contract no. HY/2011/08 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2011/08 are summarized in Table 5.6 below:
Table 5.6 Noise Monitoring Stations
for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
5.1.15
Limit level exceedance was recorded at M4b - Victoria Centre on 28 September
2020 in the reporting period.
5.1.16
No construction works was conducted under HY/2011/08 around the
monitoring location while non-CWB project material handling work immediately
next to the monitoring station was observed as the major noise contribution
during monitoring. As such, the exceedance was considered as non-Project
related.
5.1.17
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
5.2.1.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013. The baseline noise level of RTN4- Causeway Bay
Community Centre has adopted the results from the baseline noise monitoring
report for EP/364/2009 in 22 April 2010 in which approved by EPD.
5.2.2.
Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up
on 4 Sep 2012 and real time noise monitoring station RTN3 set up was performed
on 14 Sep 2012. Real time noise baseline capturing was conducted during time
period without construction work from 21 Sep 2012 to 04 Oct 2012. Real time noise monitoring at RTN3 – Po Leung Kuk Yu Lee Mo Fan Memorial School was
commenced since 06 Oct 2012.
5.2.3.
Real-time noise monitoring station RTN2 previously located at oil Street
Community Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct
2012, which is a representative of the noise sensitive receiver City Garden.
The baseline noise level of RTN2a will adopt the results derived from the
baseline noise monitoring conducted at Hong Kong Electric Centre from 4
December 2009 to 17 December 2009.
5.2.4.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
5.2.5.
With respect to the non-CWB Project building construction at Oil Street,
the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was
finely adjusted from Northeast Side to Northwestern side at Roof Top location
on 03 March 2017.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/H
5.2.6.
The proposed division of noise monitoring stations are summarized in Table
5.7 below. Real time noise monitoring for major construction works
under contract no. HY/2009/19 was commenced on 24 April 2011.
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu Lee Mo Fan Memorial School |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and
graphical presentation during restrict hours and night time period are for
information only and noise during CNP period shall be controlled under NCO.
5.2.7.
Real time noise monitoring was conducted at RTN1 - FEHD Hong Kong
Transport Section Whitfield Depot. Limit level exceedances were recorded on 30
September, 5, 6, 12, 21 and 23 October 2020 in the reporting period.
5.2.8.
After checking with the Contractor, there was no construction works
conducted under the Contractor HY/2009/19 around the monitoring station on 30
September, 5, 6, 12, 21 and 23 October 2020 during the monitoring period.
Meanwhile, renovation works was conducted at non-CWB construction site around
the monitoring station and observed as major noise contribution during
monitoring. As such, the exceedances were considered as non-Project related.
5.2.9.
No action or limit level exceedance was recorded at RTN2a - Hong Kong
Electric Centre in the reporting period.
5.2.10.
Real Time Noise Monitoring at RTN3 - Yu Lee Mo Fan Memorial School was
temporary suspended from 31 January 2020 as the school is temporarily closed
and refused our access for station maintenance due to public health concern. Real
Time Noise Monitoring at RTN3 will be resumed when the access to the school for
station maintenance is granted.
5.2.11.
No action or limit level exceedance was recorded at RTN4 – Causeway Bay
Community Centre in the reporting period.
5.2.12.
Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08 – Central - Wan Chai Bypass
(CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning
5.2.13.
The proposed division of noise monitoring stations are summarized in Table
5.8 below. Real time noise monitoring for major construction works
under contract no. HY/2011/08 was commenced on 19 March 2015.
Table 5.8 Real Time Noise Monitoring Stations for Contract no. HY/2011/08
Location
ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN4 |
Tin Hau |
Causeway
Bay Community Centre |
*Real time noise monitoring results and
graphical presentation during restrict hours and night time period are for
information only and noise during CNP period shall be controlled under NCO.
5.2.14.
Limit level exceedances were recorded at RTN1 - FEHD Hong Kong Transport
Section Whitfield Depot on 30 September, 5, 6, 12, 21 and 23 October 2020 during
daytime in the reporting period.
5.2.15.
After checking with the Contractors, no construction activities was
conducted under Contractor HY/2011/08 around the monitoring station on 30
September, 5, 6, 12, 21 and 23 October 2020. Meanwhile, renovation works was
conducted at non-CWB construction site around the monitoring station and
observed as major noise contribution during monitoring. As such, the exceedances
were considered as non-Project related.
5.2.16.
No action or limit level exceedance was recorded at RTN2a - Hong Kong
Electric Centre in the reporting period.
5.2.17.
No action or limit level exceedance was recorded at RTN4 – Causeway Bay
Community Centre in the reporting period.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.1
The commencement of construction works for HK/2009/02 under
FEP-01/364/2009 is on 26 April 2011. The proposed division of air quality monitoring
stations are summarized in Table 5.11 below.
Table 5.11 Air Quality Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.2
No action or limit level exceedance was recorded in the reporting period.
5.3.3
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/H
5.3.4
The proposed division of air quality monitoring stations are summarized
in Table 5.13 below. Air quality monitoring for the tunnel works
under contract no. HY/2009/19 was commenced on 26 April 2011.
Table 5.13 Air Quality Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Harbour Grand Hotel Boundary Wall |
CMA2a |
Causeway Bay Community Centre |
MA1b |
Harbour Building |
5.3.5
No action or limit level exceedance was recorded in the reporting period.
5.3.6
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
5.3.7 The
commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B
was on July 2014. Air quality monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.15
below.
Table 5.15 Air Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.8
As confirmed with CWB RSS, junction modification works in Central area would
be conducted by Contract HY/2010/08 starting from July 2018 and tentatively
completed in September 2018. The air quality monitoring station MA1e -
International Finance Centre (Eastern End of Podium) and MA1w - International
Finance Centre (Western End of Podium) would tentatively associated with
Contract HY/2010/08.
5.3.9
As confirmed with Resident Site Staff, the junction modification under
Contract HY/2010/08 at Central Area was generally completed while the remaining
works was considered to be no adverse impact and not related to DP works. As
such, the air quality monitoring station MA1e - International Finance Centre
(Eastern End of Podium) and MA1w - International Finance Centre (Western End of
Podium) would no longer associated with Contract HY/2010/08 in August 2019
reporting month.
5.3.10
No action or limit level exceedance was recorded in the reporting period.
5.3.11
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.3.12
Air quality monitoring for the Central Interchange works under contract
no. HY/2011/08 was commenced on 21 April 2011. The proposed division of air quality
monitoring stations are summarized in Table 5.16 below.
Table 5.16 Air Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
CMA1b |
Harbour Grand Hotel Boundary Wall |
CMA2a |
Causeway Bay Community Centre |
5.3.13
As confirmed with CWB RSS, major construction works
and landscape works associated with WVB and nearby roads under HY/2011/08 are
completed and only minor defects rectification works within WVB and tunnel area
remain, in view of the defects rectification works are minor and are carried out
in indoor area, it is considered that no adverse air quality impacts will be
caused to nearby sensitive receivers. Air quality monitoring at MA1e -
International Finance Centre (Eastern End of Podium) and MA1w - International
Finance Centre (Western End of Podium) were temporarily suspended from 16 June
2020 onwards and CMA5b - Pedestrian Plaza was temporarily suspended from 20
July 2020 onwards.
5.3.14
No action or limit level exceedance was recorded in the reporting period.
5.3.15
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.1.
Inert C&D & non-inert C&D wastes were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal
for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
Nil |
551653.03 |
TKO137, TM 38 |
Inert C&D materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D materials disposed, m3 |
2.4 |
6468.66 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
17718 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
Nil |
65663 |
South Cheung Chau |
Remarks: the conversion factor of Inert
C&D materials disposed should be 2.0.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.2.
No inert
& Non-inert C&D wastes were disposed of in this reporting period. Details of
the waste flow table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
Nil Nil |
625202.92 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT HY/2010/08 |
Non-inert C&D
materials disposed, m3 |
Nil Nil |
4675.67 1.58 |
SENT Landfill WENT Landfill |
Non-inert C&D
materials recycled, m3 |
Nil |
5496446.2 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
5.4.3.
Inert and Non-inert C&D wastes were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 5.21.
Table 5.21 Details
of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed, ton |
1081.84 |
827648.67 |
TKO137 |
Inert
C&D materials recycled, ton |
Nil |
82349.7 |
N/A |
Non-inert
C&D materials disposed, ton |
22.21 |
9024.31 |
SENT Landfill |
Non-inert
C&D materials recycled, ton |
Nil |
565.63 |
N/A |
Chemical
waste disposed, ton |
0 |
16.29 |
N/A |
Marine
Sediment (Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20737.96 |
South of Cheung Chau |
Marine
Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 –
Confined Marine Disposal), m3 |
30751 |
East of Sha Chau |
|
Marine
Sediment (Approach Ramp) (Type 2 – Confined Marine Disposal), m3 |
Nil |
6491 |
East of Sha Chau |
Contract no. HY/2010/08 Central – Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.4.
Inert and Non-inert C&D wastes were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
461.64 Nil Nil Nil |
599094.83 262656.6 82911.8 72711.86 |
TM 38 / CW / TKO137SF WENT SENT TKO area 137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
12.833 |
6626.02 |
SENT / WENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
1431 |
N/A |
Type 1 – Open Sea Disposal, m3 |
Nil |
16753.225 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined Marine disposal, m3 |
Nil |
1243.2 |
East Sha Chau |
Table 5.23 Details of Waste
Disposal for Contract no. HY/2010/08
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
5.4.5.
Inert and
Non-inert C&D wastes were disposed of in this reporting period. Details of
the waste flow table are summarized in Table 5.24.
Table 5.24 Details of Waste Disposal for Contract no. HY/2011/08
Waste
Type* |
Quantity
this month |
Cumulative-to-Date |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
8702.574 |
CWPF & TKO137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
11.211 |
9336.912 |
SENT |
Non-inert C&D materials recycled, ton |
Nil |
347.12 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
Remarks: the conversion factor of Inert
C&D materials disposed should be 2.4.
6.0.1.
The Event Action Plan for construction noise, air qualities are
presented in Appendix 6.1.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.1.
No action or limit level exceedance was recorded in the reporting
period.
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
6.1.2.
Limit level exceedance was recorded at M4b - Victoria Centre on 28 September
2020 in the reporting period. After the investigation, the exceedance was
concluded as non-Project related.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.3.
No action or limit level exceedance was recorded in the reporting
period.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
6.1.4
Limit level exceedance was recorded at M4b - Victoria Centre on 28 September
2020 in the reporting period. After the investigation, the exceedance was
concluded as non-Project related.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
6.2.1.
24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong
Kong Transport Section Whitfield Depot. Limit level exceedances were recorded
on 30 September, 5, 6, 12, 21 and 23 October 2020. After the investigation, the
exceedances were concluded as non-Project related.
6.2.2.
24-hour real time noise monitoring was conducted at RTN2a – Hong Kong
Electric Centre. No action or limit level exceedance was recorded in the
reporting period.
6.2.3.
24-hour real time noise monitoring at RTN3 - Yu Lee Mo Fan Memorial
School was temporary suspended from 31 January 2020 as the school is
temporarily closed and refused our access for station maintenance due to public
health concern. Real Time Noise Monitoring at RTN3 will be resumed when the
access to the school for station maintenance is granted.
6.2.4.
24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay
Community Centre. No action or limit level exceedance was recorded in the
reporting period.
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
6.2.6.
24-hour real time noise monitoring was conducted at RTN2a – Hong Kong
Electric Centre. No action or limit level exceedance was recorded in the
reporting period.
6.2.7.
24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay
Community Centre. No action or limit level exceedance was recorded in the
reporting period.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.3.1.
No action or limit level exceedance was recorded in the reporting
period.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/H
6.3.2.
No action or limit level exceedance was recorded in the reporting
period.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.3.3.
No action or limit level exceedance was recorded in the reporting
period.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems
and Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
6.3.1
No action or limit level exceedance was recorded in the reporting
period.
6.4.1 There was no non-compliance from the site audits in the reporting period. The
observations and recommendation
made in each individual site audit session were presented in Section 8.
7.0.1.
According to Condition 3.4 of the EP-364/2009/H, this section addresses
the relevant cumulative construction impact due to the concurrent activities of
the current projects including the Central Reclamation Phase III (CRIII), Wan
Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Final EM&A Report of Central
Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction
activities were completed by end of January 2014 and no construction activities
were undertaken thereafter and the water quality monitoring was completed in
October 2011. As such, it is considered
that there were no cumulative construction impact due to the concurrent
activities of the current projects with the Central Reclamation Phase III
(CRIII) undertaken by contractor HK12/02 in the reporting period.
7.0.3.
According to the construction programme of Central-Wanchai Bypass at
Wanchai West at the Central Reclamation Phase III area, no works was conducted
in October 2020 reporting period. In view of the above, the cumulative
construction impact due to the Central Reclamation Phase III (CRIII) was not
anticipated.
7.0.4.
According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, no construction
works under Wan Chai Development Phase II was conducted at Wan Chai. The major
construction activities under Central-Wan Chai Bypass and Island Eastern
Corridor Link Projects were ventilation building ABWF works and modification
works at Central; seabed reinstatement at Causeway Bay, drainage improvement
work and utility diversion works at Victoria Park; bridge noise enclosure
installation works, road works, drainage works, soft landscape works and
ventilation building ABWF work at North Point area in the reporting period. In
addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and
Island Eastern Corridor Link projects were observed undertaken at Wan Chai
North and North Point area.
7.0.5.
As relevant site mitigation measures for air
quality and construction noise were implemented, no significant air quality
impact and noise impact from construction activities was concluded in the
reporting period. Besides, no project related exceedance was recorded in the reporting
period. Thus, it
is evaluated that the cumulative construction impact from the concurrent
projects including Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
During this reporting period, weekly environmental site audits were
conducted for Contracts HY/2009/19, HK/2009/02 and HY/2010/08. No
non-conformance was identified during the site audits. The Contractors
rectified major observations and recommendations made during the audit
sessions.
8.0.2.
Site inspections for Contract no. HY/2009/19 were carried out during
this reporting period. No observation
was found in the reporting period.
8.0.3.
Site inspections for Contract no. HK/2009/02 were carried out during
this reporting period. No observation was found in the reporting period.
8.0.4.
As confirmed with CWB RSS, major construction works and landscape works
associated with WVB and nearby roads under HY/2011/08 are completed and only
minor defects rectification works within WVB and tunnel area remain, in view of
the defects rectification works are minor and are carried out in indoor area,
the weekly environmental site inspection for Contract no. HY/2011/08 under
EP-364/2009/H was temporarily suspended from 20 July 2020 until the resumption
of remaining construction works.
Mitigation measures implemented to prevent muddy discharge and surface
runoff
8.0.5.
With a view to ensure the adequacy and effectiveness of measures to
prevent the discharge of muddy water, including surface run-off, from
construction works, the following mitigation measures were implemented by
Contractor(s) in the reporting period:
Contract No. |
Mitigation Measures implemented |
HK/2009/02 |
·
Most of the works would
potentially generate wastewater was completed. Contractor will regular review
the muddy discharge and surface runoff concern depends on the remaining works |
HY/2010/08 |
·
Most of the land based
construction works was completed. Contractor will regular review the muddy
discharge and surface runoff concern depends on the remaining works |
HY/2009/19 |
·
Deployment of embankment along
seawall ·
Hard paved the area along seafront ·
Cover the stockpile material to
avoid excessive surface runoff ·
Avoid storage of stockpile
material along seafront ·
Regular review and maintenance of
the site drainage system ·
Regular review dosage of
wastewater treatment unit to ensure the discharge compliance |
HY/2011/08 |
·
Nil |
9.0.1.
No environmental complaints, summons and prosecution were received
during the reporting period.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3.
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
October 2020 |
0 |
September 2010 – September 2020 |
106 |
Total |
106 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
1 |
0 |
1 |
Noise |
10 |
0 |
10 |
Water |
2 |
0 |
2 |
Waste |
0 |
0 |
0 |
Total |
13 |
0 |
13 |
10.0.1.
The EM&A programme was carried out in accordance with the EM&A
Manual requirements, minor alterations to the programme proposed were made in
response to changing circumstances.
10.0.2.
The scheduled construction activities and the recommended mitigation measures
for the coming month are listed in Table 10.1. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table 10.1 Summary of Key Construction
Activities of Individual Contract(s) to be commenced in Coming Reporting period
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/19 |
·
Bridge noise enclosure construction & road works. ·
Hing Fat Street road works. ·
Soft landscaping works. ·
Open area hard paving. ·
D12 & Open Area fire main laying works. ·
D9 to D12 and P22 to P25 drainage works. ·
Rumsey Street modification works. ·
EVB injection grouting work ·
IEC Eastbound Corbel construction |
·
Noise level shall be controlled by reducing the breaking operation
rate. ·
Noise barrier shall be implemented ·
Dust control during dust generating works ·
Ensure proper deployment of silt curtain around marine construction
works area ·
Provide protection works and adequate drainage system to ensusre no
direct discharge into public drainage system or the sea. |
HY/2010/08 |
·
Drainage improvement works, ·
Utility diversion works, ·
Junction modification |
·
Dust control during dust generating works and stockpile stored on
site. ·
Appropriate measures should be taken to ensure adequate protections
are provided for trees being transplanted and retained on site. ·
Provision of protection to ensure no runoff out of site area or direct
discharge into public drainage system. |
HK/2009/02 |
·
Tunnel water seepage rectification works ·
Demolition of Site Office. |
·
Dust control during dust generating works ·
Proper maintenance boundary surface runoff protection and water
treatment facilities to avoid potential runoff related impact ·
Provision of protection measures to ensure no runoff out of site area
or direct discharge into public drainage system. ·
Strictly follow the Construction Noise Permit condition during
construction work in restricted hour and provision of control system to
ensure the permit compliance. |
HY/2011/08 |
·
Nil |
·
Nil |
10.0.3.
The construction works of Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
was completed, and the FEP was surrendered by the Contractor on 11 February
2011.
10.0.4.
The construction works of Contract no. HY/2009/17 - Advance piling works
at Whitfield Depot under FEP-03/264/2009 was completed, and the FEP was
surrendered by the Contractor and found in order by EPD on 25 April 2013.
10.0.5.
The construction works of Contract HK/2010/06 was completed, and the
FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.
10.0.6.
The Construction works under HY/2009/15 was confirm completed by the RSS
from 27 October 2017 onwards.
As confirmed by CWB RSS, the seabed reinstatement works was resumed
under Contract HY/2009/15 at EX-PCWA area on 26 June 2019 and the weekly site
audit inspection and the associated monitoring station for HY/2009/15 were
resumed from 26 June 2019 onwards and report under FEP-04/356/2009 in
EP-356/2009 Monthly EM&A Report.
10.0.7.
The Construction works under HY/2009/18 was confirm completed by the RSS
from 25 April 2018 onwards
10.0.8.
As confirmed with WDII RSS and with respect to the joint inspection
conducted with IEC on 25 May 2018, RSS, ET and IEC share the view that there is
no adverse environmental impact of remaining works under Contract HK/2009/01
and the respective environmental site inspection was temporary suspended from
26 May 2018 onwards. FEP-02/364/2009 was surrendered by the Contractor on 3 September 2018.